6 Jan 2024
Calm morning before the New Year holiday finishes.
23 Oct 2023
The Plot 4 jigsaw is underway
16 OCT 2023
One morning's work. Danwood have the ground floor walls up on Plot 5
2 Oct 2023
After 1 week
25 Sep 2023
3pm on Day 1
20 Sep 2023
Plot 9 Scaffolding
11 Sep 2023
1st of 3 Autumn builds on its way.
14th July 2023
German tanks roll in. Graf sewage treatment plants for plots 4 and 5
12th July 2023
The Dan Wood site manager seems happy after inspecting progress
7th July 2023
Pouring again. The third and final section of double reinforced concrete pad.
3 June 2023
Plot 9. Sand is levelled. Shuttering accurately position.
28 June 23
Under floor engineering has to be exact
24 06 23
Remember those seed packs?
22 June 23
Plot 4 Concrete in trenches
17 June 2023
"Bar": noise traditionally made by sheep in Barhill. "Leana": Gaelic for meadow.
14 June 2023
Plot 9 now out of the ground
6 June 23
The first foundations.
5 May 23
Old electricity poles go. Meanwhile a pheasant is nesting a few feet away.
15 April 23
14 April 2023
Plot 5 platform
13 April 2023
Great Wall
12 April 2023
Ground breaking. Plot 4 getting ready for foundations.
26 Mar 2023
Sunday a day of rest
22 Mar 2023
Plots 9,10,11 & 12 getting a makeover
7 March 2023
Extensive nature programme continues with two more ponds
26 Feb 2023
Two ponds shaping up
24 Feb 2023
Young couple thinking of settling in Barleana
23 Feb 2023
Various seeds are arriving and the pigeons are licking their beaks
20 Feb 2023
The water in the foreground has many frogs and much spawn waiting for the pond in the background to be completed.
8 Feb 2023 4 inch telecom ducting telecom will take fibre optical cable in the future
01 Feb 2023 250m = 1 drum. The heavy 185 Quad Core cable is joined to the next length.
26 Jan 23 Digging for Electricity
24 Jan end of the line for water
19 Jan 23 300 metres in
16 Jan 23 Another early start
9 Jan 23 Utilities are coming